Use this screen to select one or more estimate lines and compare the cost to a recycled assembly.
Description of fields on the Estimate tab screen
Field Label | Description |
---|---|
Line | This is the estimate line number. Select one or more to begin the comparison. |
Operation | This value is the operation type of the selected estimate line. |
Description | Description of the part or labor operation. |
Quantity | This pertains to the number of parts in the selected estimate line. |
Ext. Price $ | This value is calculated from the price of the part multiplied by the quantity. |
Labor Hours / Paint Hours | Any labor hours associated with the selected estimate line appear in these fields. |
Estimate Lines - Category Hours Price $ |
These values are summed as you select one or more estimate lines for comparison. |
Recycled Assembly - Hours Adds Price $ |
Values in these fields are taken from the Recycled Assembly tab information. |
Difference _ Price $ | These vales represent the cost difference of the selected estimate lines compared to the cost of the recycled assembly. |
Replace with Recycled | Select this option to replace the selected estimate lines and add the recycled assembly to the estimate. |
Cancel | Selecting this option closes the screen without adding. |
Description of fields on the Recycled Assembly tab screen
Field Label | Description |
---|---|
Description | Enter a description of the recycled assembly as it will appear in the estimate line. |
(search button) | Select this button to search and select recycled suppliers with the associated parts. |
Parts Cost $ | Enter the base cost amount. If you selected the assembly from the Select Recycled Parts screen, that value displays instead. |
Parts Markup $ | Enter the markup amount. If you selected the assembly from the Select Recycled Parts screen, that value displays instead. |
Labor Category | Body is the default value. You can select a different labor category from the droplist. |
Labor Hours Paint Hours |
Enter the labor hours in these fields. If you selected the assembly from the Select Recycled Parts screen, those values display instead. |
Estimate Lines - Category Hours Price $ |
These values are summed as you select one or more estimate lines for comparison. |
Recycled Assembly - Hours Adds Price $ |
Values in these fields are taken from the Recycled Assembly tab information. |
Difference _ Price $ | These vales represent the cost difference of the selected estimate lines compared to the cost of the recycled assembly. |
Replace with Recycled | Select this option to replace the selected estimate lines and add the recycled assembly to the estimate. |
Cancel | Selecting this option closes the screen without adding. |